Brevard South Reach Performance
Years of Post Construction Date of Survey Volume Above -16' Volume Above MHW
Remaining (%) Changes* (cy/ft) Remaining (%) Changes* (cy/ft)
Avg.MaxMin Avg.MaxMin
0 5-2003 100 75103 25 100 29 40 10
1 6-2004 89 67 9816 97 284017
0 5-2005 100 7010017 100 2944 2

 
Brevard South Reach Performance
Years of Post Construction Date of Survey Shoreline (MHW) Changes* (ft.)
Avg.Max.Min.
0 5-2003 101130 44
1 6-2004 92137 53
0 5-2005 99148 -4

 