|
|
Delray Beach Summary & Conclusions |
| |
From the Coastal Planning & Engineering (CP&E) June 1994 Report
(Reference):
- In the 12 months since construction 122,000 cubic yards of sediment has eroded from the
total Delray Beach study area. This loss is comparable to previous first year losses after
the renourishments at Delray Beach.
- The shoreline since the 1992 construction has retreated an average of 35.2 feet. The
rapid shoreline loss is expected post-construction as the construction beach develops
toward the natural equilibrium shoreline. Based on previous projects, it is expected that
this loss will slow down over the next year.
From the Coastal Planning & Engineering (CP&E) July 1995 Report
(Reference):
- In the 24 month period following the completion of the project the MHW shoreline retreated an
average of 65.2 feet. The high erosion and shoreline loss seen in the first and second years
post-construction is similar to losses seen following the 1973, 1978 and 1984 projects. The high
losses may also be related to Tropical Storm/Hurricane Gordon which impacted the coastline of
Delray Beach November 15 through 19, 1994, three weeks prior to the survey.
From the Coastal Planning & Engineering (CP&E) June 1996 Report
(Reference):
- The shoreline since the 1992 construction has retreated an average of 52.7 feet. As
occurred in previous Delray Beach projects, the shoreline acreted (+12.6 feet) between
two year and three year surveys. This appears to be the result of the shoreline and profile
reaching equilibrium and as a result becoming somewhat more stable.
From the Coastal Planning & Engineering (CP&E) October 1998 Report
(Reference):
- The project area mean high water shoreline is an average of 62 feet wider than the pre-construction
shoreline position.
The shoreline has reached an equilibrium condition relative to the construction profile and has
become somewhat more stable.
From the Coastal Planning & Engineering (CP&E) April 2000 Report
(Reference):
- The project area mean high water shoreline is an average of 33 feet wider than the 1992
pre-construction shoreline position. Between January 1999 and February 2000, the
shoreline in the project area receded an average of 25 feet. This recession rate is an
acceleration compared to the trend of recent years, and is likely the result of a high wave
climate during the year, dominated by Hurricanes Dennis, Floyd, and Irene.
From the Coastal Planning & Engineering (CP&E) September 2003 Report
(Reference):
- Since 1973, the City of Delray Beach has conducted five beach restoration projects using sand from
offshore of the City. Approximately 6 million cubic yards of sand has been placed as a result of the
City's beach preservation efforts. A volume of 3.8 million cubic yards, or 63% of the total volume
placed since 1973 remains within the City limits. Since the initial nourishment of 1973, the City has
maintained the beach through beach renourishment on four occasions, including 1978, 1984, 1992
and 2002.
- The fourth periodic beach renourishment project constructed by the City of Delray Beach was built
in February and March of 2002.
- The one year post-construction survey (March 2003) indicated that the expected adjustment
to natural equilibrium slope had progressed. During the two year post-construction period, sand is
expected to continue to move offshore until the system reaches a natural equilibrium slope.
Shoreline measurements taken in March 2003 have documented an average advance of 190 feet over
the project area, compared to the pre-construction condition.
From the Coastal Planning & Engineering (CP&E) August 2004 Report
(Reference)
- Of the 1,230,000 cubic yards placed in 2002, the May 2004 survey indicated that 915,760 cubic yards
(or 74%) of the original fill remains within the project area. In the center of the project area
between DEP monuments R-181 to R-187 approximately 56% of the original fill remains.
|
|