|
|
Jupiter / Carlin Summary & Conclusions |
| |
From the Taylor Engineering 2002 Report
(Reference)
- Nourishment activities involved movement of sediment within the active profile rather than
reintroduction of previously lost material.
- The March 1996 storm significantly impacted the area and induced widespread cross-shore
movement of sediment beyond the limits of the profile surveys.
- This storm was the primary cause of the projects poorer than expected performance during the first
year following construction.
- The borrow site filled rapidly due in large part to the cross-shore movement of material associated
with the storm and longshore bypassing.
- The tidal channel reoriented southward following the deep water associated with the borrow area.
From the Applied Technology & Management 2004 Report
(Reference)
- In the first 12-months following project construction, the project area shows that approximately 537,400 cy
or 86 percent of the renourishment project volume remained in the project area (above -22 ft NGVD).
- No additional hardbottom was covered due to the renourishment project.
- The average increase in berm width in the project area at the time of the 12-month
post-construction survey was approximately 110 feet.
- The ebb shoal gained approximately 65,000 cy between December 2002 and December 2003.
- Moderate project spreading was observed downdrift of the project area.
|
|