Jupiter / Carlin Main Page
 
Location Map
 
Design Parameters
 
Shoreline Change Plots
 
Volume Change Plots
 
Hot Spots
 
Performance Table
 
Performance Summary
 
 
Project Index

Jupiter / Carlin Summary & Conclusions

 
From the Taylor Engineering 2002 Report (Reference)
  • Nourishment activities involved movement of sediment within the active profile rather than reintroduction of previously lost material.
  • The March 1996 storm significantly impacted the area and induced widespread cross-shore movement of sediment beyond the limits of the profile surveys.
  • This storm was the primary cause of the projects poorer than expected performance during the first year following construction.
  • The borrow site filled rapidly due in large part to the cross-shore movement of material associated with the storm and longshore bypassing.
  • The tidal channel reoriented southward following the deep water associated with the borrow area.
From the Applied Technology & Management 2004 Report (Reference)
  • In the first 12-months following project construction, the project area shows that approximately 537,400 cy or 86 percent of the renourishment project volume remained in the project area (above -22 ft NGVD).
  • No additional hardbottom was covered due to the renourishment project.
  • The average increase in berm width in the project area at the time of the 12-month post-construction survey was approximately 110 feet.
  • The ebb shoal gained approximately 65,000 cy between December 2002 and December 2003.
  • Moderate project spreading was observed downdrift of the project area.

© 2003-2005 Beaches & Shores Resource Center
Florida State University