Jupiter / Carlin

 
*Changes from March-95 Pre-Construction
Jupiter / Carlin Performance
Years of Post Construction Date of Survey Volume Above MHW
Remaining (%) Changes* (cy/ft)
Avg.MaxMin
05-1995 100404730
0.511-1995 5923413
15-1996 6528488
25-1997 6628804
36-1998 5421543
46-1999 411441-5
57-2000 321128-10
67-2001 441544-12

 
Jupiter / Carlin Performance
Years of Post Construction Date of Survey Shoreline (MHW) Changes* (ft.)
Avg.Max.Min.
05-1995 163201143
0.511-1995 831843
15-1996 11621023
25-1997 10628622
36-1998 742046
46-1999 45161-40
57-2000 3897-34
67-2001 53197-39

 

 
*Changes from July-2001 Pre-Construction
Jupiter / Carlin Renourishment Performance
Years of Post Construction Date of Survey Volume Above MHW
Remaining (%) Changes* (cy/ft)
Avg.MaxMin
010-2002 100385311
1 7-2003 81304520
27-2004 68263716

 
Jupiter / Carlin Renourishment Performance
Years of Post Construction Date of Survey Shoreline (MHW) Changes* (ft.)
Avg.Max.Min.
010-2002 124166 64
17-2003 11015960
27-2004 8411557

 