Jupiter Island |
| |
*Changes from June-95 Pre-Construction
| Jupiter Island Performance |
| Years of Post Construction |
Date of Survey |
Volume Above -15' |
Volume Above MHW |
| Remaining (%) |
Changes* (cy/ft) |
Remaining (%) |
Changes* (cy/ft) |
| Avg. | Max | Min |
Avg. | Max | Min |
| 0 | 7-1996 |
100 | 57 | 88 | 2 |
100 | 32 | 46 | 12 |
| 1 | 6-1997 |
89 | 53 | 106 | 18 |
73 | 24 | 44 | 5 |
| 2 | 6-1998 |
76 | 45 | 116 | 7 |
63 | 21 | 50 | 3 |
| 3 | 6-1999 |
134 | 77 | 130 | 31 |
79 | 26 | 45 | 14 |
| 4 | 6-2000 |
101 | 58 | 118 | -5 |
68 | 22 | 46 | 3 |
| 5 | 6-2001 |
101 | 54 | 143 | 1 |
65 | 21 | 37 | 5 |
| Jupiter Island Performance |
| Years of Post Construction |
Date of Survey |
Shoreline (MHW) Changes* (ft.) |
| Avg. | Max. | Min. |
| 0 | 7-1996 |
121 | 198 | 29 |
| 1 | 6-1997 |
71 | 122 | 17 |
| 2 | 6-1998 |
67 | 134 | -8 |
| 3 | 6-1999 |
95 | 145 | 47 |
| 4 | 6-2000 |
70 | 156 | 20 |
| 5 | 6-2001 |
65 | 111 | 10 |
|
|