|
|
Pensacola Beach Summary & Conclusions |
| |
From the Olsen Associates, Inc. 2003 Report
(Reference)
- Construction of the project resulted in an average advance of the Mean High Water Line of 191 ft (exclusive
of tapers). This average advance reflects a portion of the expected EQUILIBRATION of the beach
fill project in which the initially constructed beach berm is expected to recede over the initial stages of
the project life.
- Some degree of episodic equilibration has occurred due to the impacts of Tropical Storm Bill at the end
of June 2003. Construction was approximately 85% complete when Bill made landfall. For
comparison, the design construction berm width averaged 225 ft. In the limit, equilibration of
the beach fill project may reduce the beach width to roughly 125 ft. Until complete equilibration
occurs, or, more likely, until tropical storms further impact the shoreline, the beach will remain wider
than the predicted post-equilibration design width.
From the Olsen Associates, Inc. 2004 Report
(Reference)
- Shoreline position and beach volume changes over the Year-1 intersurvey period are strongly characterized
by the ongoing equilibration process.
- Over the first 9 to 15 months post-construction, the 8.1 miles of Gulf of Mexico shoreline within the project
limits receded an average of 53 feet, primarily as part of the equilibration process. At the
same time, volumetric calculations reveal that the sand transported from the upper
portion of the beach can be found in the trough area within only a few hundred feet from
the shoreline (on average).
From the FDEP 2005 Report
(Reference)
- At about 2:25 PM CDT, July 10, Hurricane Dennis made landfall approximately two miles east of Pensacola
Beach near Big Sabine Point on Santa Rosa Island. Pensacola Beach was generally in the weaker
leeside eye-wall and experienced winds in probably the category II range (95-115 mph). A peak
wind of 93 mph was measured in Pensacola by the National Weather Service.
- Minor beach erosion was sustained along Pensacola Beach. The erosion did not leave any
scarping, and new constructed dunes were not significantly damaged. A major beach restoration
project was completed here in 2003, and the Santa Rosa Island Authority was in the process of
nourishing the beach to pre-Ivan design.
From the Olsen Associates, Inc. 2007 Report
(Reference)
- Volume changes measured between May 2004 (pre-Ivan) and May 2007 reveal only minor erosion above -14 ft NAVD88,
on the order of 13,000 cy (~0.3 cy/ft). This result indicates the general success of the renourishment
project, the objective of which was to replace the sand volume lost during Hurricane Ivan. As documented
by surveys after each major storm (Ivan, Dennis, and Katrina), significant fractions of the sand lost during
these events were transported Gulfward beyond the primary bar. Survey comparisons to closure indicate
that an estimated 2.1 Mcy (approx.) resides at or offshore of the primary bar crest. Experience from
previous storm impacts suggests that this sand will be slow to return to the active beach face, and some portion
of the sand volume may likely be carried away by alongshore currents during that process, such that a net loss of
the bar sand may occur.
|
|